CGN Delingha 200MW Molten Salt Tower Solar Thermal Project 80% Completed

Updated:2025-04-22 20:58Source:CSTA
On April 17, a China News Service journalist visited the CGN Delingha 200-megawatt molten salt tower solar thermal power project, which is currently under construction and is China's largest single-unit solar thermal project. At the construction site, the solar thermal turbine set has been positioned and is undergoing installation adjustments.
At the construction site of the CGN Delingha 200-megawatt solar thermal power generation project with energy storage on April 17 (photographed by Ma Mingyan).
According to the project manager, all core equipment for the project has been positioned, with 80% of the construction progress completed. The project is expected to be finished within the year.
 