On April 13th, the 10,000th heliostat for the 100MW molten salt tower CSP plant of the 100MW CSP + 900MW renewable energy project in Bortala (shortened as "Bortala Project"), undertaken jointly by SunSum Technology Co., Ltd.(" SunSum ") and Gansu Province Installation & Construction Group Co.,Ltd.as the PC general contractor for the CSP plant of New China Hydropower Company, was successfully assembled and taken offline. This achievement has laid a solid foundation for the plant's goal of full-capacity grid connection in 2025.
As the equipment supplier for the concentrated heat collection system of the Bortala Project, SunSum has carefully established an intelligent heliostat assembly workshop at the construction site of the CSP plant. Since the first heliostat was successfully taken offline, the heliostat manufacturing team of SunSum has continuously optimized the process flow and closely carried out technical cooperation, effectively advancing the project construction.