Xinjiang Shanshan 100MW Solar Thermal Power Project: All Heliostats Installed

Updated:2025-01-02 10:16Source:CSTA

On December 17th, the Xinjiang Shanshan Qiketai 100,000-kilowatt solar thermal power project, which was contracted and constructed by SDEPCI, achieved two major milestones: the completion of the assembly and delivery of all heliostats, and the completion of the installation of all heliostats, marking the full entry into the debugging phase of the concentrating system.

It is reported that the project has a total of 16,667 heliostats, with a mirror field area of 500,000 square meters, divided into 16 construction sections.