Two PV+ Concentrated Solar Power Projects Started in Xinjiang

Updated:2022-07-20 13:58Source:helioscsp

On July 9, PowerChina Xinjiang Ruida New Energy 100 MW Concentrated Solar Power + 900 MW PV project groundbreaking ceremony was held at 22 kilometers south of Yitumbulak town in Ruoqiang County.

The project is located 18 km north of Yitumbulak town in Ruoqiang County, Bazhou, Xinjiang, 170 km southeast of Ruoqiang County. The project will be completed and transmitted to the 220 kV substation through 220 kV convergence station.

Turpan City, Tuokexun County, 100MW CSP +900MW PV projec

The 100MW CSP (energy storage) + 900MW PV project in Tuokexun County, Tulufan City, of which PowerChina SOCOL Corporation is the general contractor, started construction recently.

The project is located in Tuokexun County, Tulufan City, Xinjiang, 6 km south of provincial road S301 and north of Wusitonggou Reservoir, with a total project site area of 249.83 hectares.