How ACWA Bid Record Low Cost CSP in Dubai

Updated:2017-09-25 14:21Source: New Energy Update
The giant 700 MW project in Dubai will combine tower and trough technologies and use scale and local infrastructure synergies to set a new benchmark price of $73/MWh for CSP with storage, Andrea Lovato, ACWA Power’s Executive Director of Business Development, told New Energy Update.
ACWA Power will use learnings from its Noor CSP project in Morocco which also uses tower and trough technology.
On September 16, the Dubai Electricity and Water Authority (DEWA) awarded Saudi Arabia’s ACWA Power a 700 MW CSP project following a highly competitive tender launched earlier this year.
The project represents the fourth development phase of the Mohammed bin Rashid Al Maktoum (MBR) Solar Park which will host 1 GW of solar capacity by 2020, rising to 5 GW by 2030.
ACWA Power’s plant is expected to cost AED14.2 billion ($3.9 billion) and ACWA Power is to commit $750 million equity to the project. Consortium partners will include China’s Shanghai Electric and DEWA has also said it plans to invest in the plant.
The project represents the world’s largest single-site CSP plant based on the Independent Power Producer (IPP) model and will use a combination of central tower and parabolic trough technologies.
The tower will be 260 meters high, equivalent to the Emirates Towers skyscrapers in Dubai. The plant will use molten salt storage to produce power through the night and complement rising daytime PV capacity.
ACWA Power’s 700 MW project is far larger than the 200 MW requirement set out in DEWA’s tender criteria and establishes new cost benchmarks for the growing Middle East CSP market.
Economies of scale will lower project capital expenditure (capex) through bulk orders and improved infrastructure and construction logistics, Lovato told New Energy Update.
“Opex [Operational expenditure] savings can also be achieved using common infrastructure and operations and maintenance personnel in the UAE,” he said.
 
Dual technologies
DEWA received 30 Expressions of Interest for the CSP project, represented by 34 regional and global companies. Six consortia were shortlisted for the Request for Proposal (RfP) phase.
Dubai had targeted a cost of $80/MWh but technology and efficiency gains in other countries had indicated lower costs were possible.
DEWA called for twin tower technology designs but said alternative designs could be submitted provided they fulfilled tender criteria. Plants had to be able to generate power from 4 pm to 10 am, requiring bidders to focus on cost-efficient storage designs.
ACWA Power’s tower system will provide fifteen hours of storage while the trough section will provide eleven hours. The combination of technologies will help to reduce the total cost of energy, Lovato said.
“Parabolic troughs are a more mature and low-risk technology while tower technology and energy storage help reduce costs,” he said.
While current installed CSP capacity is dominated by parabolic trough systems, data from the CSP Today Global Tracker shows that solar towers account for nearly half of global capacity under construction and 70% of projects under development. Recent growth in tower deployment is mainly driven by the ability to achieve higher temperatures than other CSP technologies, raising plant efficiencies and providing lower storage costs.
ACWA Power is already deploying a combination tower and trough of technology at the NOORo Solar Complex in central Morocco. Noor I, a 160 MW CSP parabolic trough plant, is operational. The 200 MW Noor II parabolic trough plant and 150 MW Noor III tower plant have both reached financial closure and are under construction.
“Use of this [combination of] technology has allowed for increased storage capacity,” Lovato noted.
   CSP plants under construction in the Middle East
Chinese input
DEWA’s tender criteria did not enforce local content requirements and Shanghai Electric’s involvement in the engineering, procurement and construction of the project will help drive down costs.
Shanghai Electric is currently building CSP capacity in China as part of the country’s ambitious targets to complete 20 CSP projects of total capacity 1.3 GW by 2018. This first batch of Chinese projects is expected to accelerate deployment efficiencies and build out China’s CSP supply chain.
“In order to deliver reliable power at the lowest possible cost, ACWA Power looks to incorporate local content where possible, as well as work with our existing network of suppliers in the markets where we operate to achieve economies of scale and reduce cost,” Lovato said.
Prices of CSP equipment in China, including steam turbines, generators and receivers are already falling faster than in western markets, Xavier Lara, executive director at engineering group Empresarios Agrupado, told New Energy Update in April.
The creation of a domestic CSP industry in China will allow EPC contractors to export their expertise and this will further reduce costs, he said.
“This will please developers and offtakers in the MENA [Middle East and North Africa] region because it will cut prices dramatically,” Lara said.
ACWA Power also expects savings in financing costs due to DEWA’s strong credit rating, the political stability of UAE, and the current low interest rate environment.
In 2016, Dubai set the world’s lowest PV price of $29.9/MWh for the 800 MW MBR phase 2 project, demonstrating the significant banking interest and cost reduction potential of Dubai’s solar program.
 
Benchmark project
ACWA Power’s equity investment in the 700 MW project represents the company’s largest ever capital commitment.
The power purchase agreement (PPA) and financial closure of the project are expected to be finished “shortly,” DEWA said in a statement.
Construction is expected to commence in early 2018 and the first phase of the project is expected to be completed by the end of 2020.
The record-low CSP price for the Dubai project comes as several other Middle East and North Africa countries look to take advantage of strong solar resources and diversify from hydrocarbons.
UAE and Morocco have been front-runners in solar power development but countries such as Saudi Arabia and Kuwait are accelerating deployment.
Earlier this year, Saudi Arabia’s newly-created Renewable Energy Project Development Office (REPDO) said it plans to build 1 GW of CSP capacity by 2023.
 

Hot list

Recommended