SUPCON SOLAR Delingha 50MW Concentrated Solar Power Plant released the latest operation data

The total power generation of the plant was 14.571GWh in September, with achieving rate of 99.98%, and the following October, the monthly power generation of the plant was 13.671GWh, with achieving rate of 102.25%.

From 26th of Aug to 25th of Sept., total DNI 193.77KWh/m2, Concentrated Solar Power plant practically generated 14.571GWh on the basis its theoretical designed capacity with 14.574GWh, achieving 99.98%. Total 13.550GWh was connected in grid, cumulative generation with 440.22 hours. Except of 5 days in cloudy, actual operating 26 days, 14 days among it reaching 100% capacity.

From 26th of Sept to 25th of Oct., total DNI 169.81KWh/m2, CSP plant practically generated 13.671GWh on the basis its theoretical designed capacity with 13.371GWh, achieving 102.25%. Total 12.649GWh was connected in grid, cumulative generation with 436.22 hours. Except 5 days in cloudy, actual operating 25 days, 15 days among it reaching 100% capacity.

SUPCON SOLAR Delingha 50MW Molten Salt Tower CSP Plant, one of China’s CSP Demonstration projects, is installed with a 7-hour molten salt storage system and designed to generate 146GWh electricity annually. The project is designed and constructed based on Cosin Solar’s fully patented technologies, over 95% equipment are domestically sourced.