Morocco Noor III Project Air Blowing Finished Successfully

Updated:2018-04-09 12:03Source:SEPCO III
On Apr 2nd,2018, Morocco Noor III Project air blowing finished successfully.
Air blowing was 288 times lasted for 25 days. In the process of air blowing, blow the pipe 24 hours a day. The standard passed the acceptance and the blow pipe work was successfully completed. The successful completion of air blowing makes a solid foundation for the smooth start-up of the follow-up steam turbine