Lanzhou Dacheng 50MW molten salt Fresnel CSP project completes over 85% work

Updated:2019-10-15 18:52Source:CSPPLAZA
Lanzhou Dacheng 50MW molten salt Fresnel CSP project is one of China’s first batch of CSP demonstration projects. The project has an installed capacity of 50MW and is equipped with a 15-hour molten salt heat storage system. The designed annual power generation capacity is 214 million kWh, and the annual utilization hours are 4283 hours.
 
 
The project strives to be completed and put into operation at the end of this year.
 
Up to now, more than 85% of the construction work of the project has been completed with 90% of the equipment on site and solar field installation completing 60%. By the end of August, the project had closed an investment of about 930 million yuan.